Wednesday, February 22, 2006

Digging begins for the footers


The area is compacted and at grade so we are trenching for the footers. Forming will continue through next week.

Wednesday, February 15, 2006

Excavation begins


Following digging approval, the topsoil is scraped off and the site prepared for a soil compaction test

Wednesday, February 08, 2006

Demolition is finished


Demolition has been completed on both phases of the project and we are ready to start excavation by Monday once utility digging markings are finished