Thursday, February 22, 2007

Framing and Insulation



The framing is done and inspected, the insulation is up and ready for inspection. The sheetrock is being delivered to start installing

Monday, February 12, 2007

Stucco work is done



The stucco is done and texture applied. The next step is to apply all the foam trim pieces.

Thursday, December 21, 2006

Roofing continues



After inspection passed, the roofing is continuing with the flat roof insulation and hot mop. The stucco work on the parapet is already done so the roof can be sealed against it.

Friday, December 15, 2006

Doors and Stucco



While the electrical, plumbing and A/C continue, the French doors were installed and the stucco work started.

Thursday, December 07, 2006

Progress on Many Fronts



The windows are mostly installed, the plumber, electrician and framer are almost done and the stucco is getting started. The roofer is scheduled for tin cap inspection on Friday and the rough stairs are also installed.

Friday, September 15, 2006

Sheathing the Roof



The final cap beams and parapets are poured, the trusses in place and the roof plywood is ready for inspection on Monday. The precast window sills are being installed so the window bucks can be started tomorrow

Wednesday, August 16, 2006

Final blocks are going up



The last blocks for the parapets and party wall are going up now. The next few days will be for preparing the walls for trusses to be flown into place on Friday.